We purchased 2 EX4600's and I created 4 VC ports, connected 4 40gig QSFP cables and preprovisions the virtual chassis. The virtual chassis is up and running. I have successfully done this on many EX3300 switches. I need to verify that the virtual chassis is in fact using all 4 40gig ports to maximize our total throughput. This looks a bit different to me than the EX3300's and I never used 4 cables, only 2 in the past.
I am just looking for how to verify all 4 cables are working. Any asistance is greatly appreciated.
Thank you.